4.7.5 Message Definitions

4.7.5.1 OCNMFD - Surplus Forecast 2-14 days ahead


This message contains peak-of-the-day surplus forecast values for the following 2 weeks. The data is published by BMRA as it is received from the System Operator . The Publishing Time in the message is applicable to the forecast as a whole. The records in the message are ordered by time.

Message Definition

The following table lists the fields that are required in the message.



Field

Field Type

Description of field

Publishing Date

TP

The time that the data was originally published by the System Operator .

Number of records

NR

The number of times the next THREE fields are repeated.

Settlement Date

SD

The settlement date.

Settlement Period

SP

The settlement period.

Margin/Surplus Value

VM

The surplus in MW.

Message Subject Name

BMRA.SYSTEM.OCNMFD


4.7.5.2 OCNMFW - Surplus Forecast 2-52 weeks ahead


This message contains peak-of-the-week surplus forecast values for the following year. The data is published by BMRA as it is received from the System Operator . The Publishing Time in the message is applicable to the forecast as a whole. The records in the message are ordered by time.

Message Definition

The following table lists the fields that are required in the message.



Field

Field Type

Description of field

Publishing Date

TP

The time that the data was originally published by the System Operator .

Number of Records

NR

The number of times the next THREE fields are repeated.

Calendar Week Number

WN

The number of the week.

Week Start Date

WD

The start date of the week (in GMT).

Margin/Surplus Value

VM

The Surplus in MW.

Message Subject Name

BMRA.SYSTEM.OCNMFW


4.7.5.3 NDFD - Demand Forecast 2-14 days ahead


This message contains peak-of-the-day demand forecast values for the following 2 weeks. The data is published by BMRA as it is received from the System Operator . The Publishing Time in the message is applicable to the forecast as a whole. The records in the message are ordered by time.

Message Definition

The following table lists the fields that are required in the message.



Field

Field Type

Description of field

Publishing Date

TP

The time that the data was originally published by the System Operator .

Number of Records

NR

The number of times the next THREE fields are repeated.

Settlement Date

SD

The settlement date.

Settlement Period

SP

The settlement period.

Demand Value

VD

The demand in MW.

Message Subject Name

BMRA.SYSTEM.NDFD


4.7.5.4 TSDFD – Transmission System Demand Forecast 2-14 days ahead


This message contains peak-of-the-day Transmission System demand forecast values for the following 2 weeks. The data is published by BMRA as it is received from the System Operator. The Publishing Time in the message is applicable to the forecast as a whole. The records in the message are ordered by time.

Message Definition

The following table lists the fields that are required in the message.



Field

Field Type

Description of field

Publishing Date

TP

The time that the data was originally published by the System Operator .

Number of Records

NR

The number of times the next THREE fields are repeated.

Settlement Date

SD

The settlement date.

Settlement Period

SP

The settlement period.

Demand Value

VD

The demand in MW.

Message Subject Name

BMRA.SYSTEM.TSDFD