Attachment 2: sample contract part I the schedule section b supplies or services and prices/costs b-1 type of contract and total contract value




Дата канвертавання21.04.2016
Памер82.44 Kb.
ATTACHMENT 2: SAMPLE CONTRACT
PART I - THE SCHEDULE
SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS
B-1 TYPE OF CONTRACT AND TOTAL CONTRACT VALUE
The Contractor shall, in accordance with the terms and conditions set forth herein, furnish the necessary qualified personnel, services, travel, facilities and materials (except those specifically designated to be provided by the Government) and do all things necessary and incidental to complete the contractual effort in accordance with the Statement of Work incorporated by Section C - Description/Specifications/Statement of Work hereto. 
The total current contract value is TBD (Not to exceed (NTE) $350,000).
CLIN 0001, as identified in this contract and in the total estimated amounts set forth below are FP/FFP, as described under the Federal Acquisition Regulations (FAR) 16.202.
Description: DII project entitled TBD in accordance with contractor's proposal dated TBD.


Firm Fixed Price

TBD (NTE $350,000)

Total

TBD (NTE $350,000)

The total value for the Contract Line Item 0001, and any modifications thereto are shown below. (Note: Provisional increases are not included in this summary until recognized as definitive).







Firm Fixed Price

Total

P00000

TBD (NTE $350,000)

TBD (NTE $350,000)

CLIN 0002, as identified in this contract and in the total estimated amounts set forth below are NSP/NSP, as described.


Description: Data and Reports: The contractor shall, at a minimum, submit monthly reports, conduct an interim review, conduct a final review and submit a final report. Interim reviews may be conducted via telecon, VTC, or other remote connection. The final review shall be presented at NRO Headquarters, Chantilly, VA and may include an NRO Technology Seminar presentation of approximately one (1) hour in duration.

SECTION C - DESCRIPTION/SPECS./WORK STATEMENT
C-1 Statement of Work
The Government's Statement of Work entitled TBD dated TBD is incorporated and made part of this contract as Attachment 1 to Part III of Section J hereto.

SECTION D - PACKAGING AND MARKING
D-1 Packaging and Marking
Packaging and marking of deliverable items called for hereunder shall be in accordance with: 
(1) the Contractors best commercial practice and 
(2) any delineated requirements in the Statement of Work required to insure safe arrival at the destination.

SECTION E - INSPECTION AND ACCEPTANCE
E-1 52.246-9 Inspection of Research and Development (Short Form) (APR 1984)
The Government has the right to inspect and evaluate the work performed or being performed under the contract, and the premises where the work is being performed, at all reasonable times and in a manner that will not unduly delay the work. If the Government performs inspection or evaluation on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties. 

SECTION F - DELIVERIES OR PERFORMANCE
F-1 N52.252-002 Clauses Incorporated by Reference (MAR 2001)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The full text of each clause may also be accessed electronically at this address: http://arc.westfields.net/nam.


Number

Title

52.242-15

Stop-Work Order (AUG 1989)



F-2 N52.211-006 Contractor Performance And Delivery (MAR 1996)
(a) Period of Performance: The period of performance of this contract shall be:


CLIN

Start Date

Completion Date

0001

TBD

TBD

0002

TBD

TBD

The principal place of performance under this contract shall be the contractor's facility  located at:  Reference Section K, 52.215-6, "Place of Performance."  


(b) Delivery: In the event an item under this contract is delivered directly to the COTR, the contractor shall obtain a signed receipt from the COTR. One copy of the receipt shall be attached to the contractor's invoice submitted for payment for such item(s). Failure to do so may result in delayed payment.
(c) When the contractor encounters difficulty in meeting performance requirements, or anticipates difficulty in complying with the contract delivery schedule or date, they shall immediately notify the Contracting Officer in writing giving pertinent details; provided, however, that this data shall be informational only in character and that this provision shall not be construed as a waiver by the Government of any delivery schedule for any rights or remedies provided by law or under this contract.

PART II - CONTRACT CLAUSES
SECTION G - CONTRACT ADMINISTRATION DATA
G-1 GOVERNMENT POINTS OF CONTACT
Title Name Phone Number

Contracting Officer Scott Meder 703-808-4675

COTR LtCol John Comtois 703-808-1907



G-2 PURCHASE REQUEST NUMBER AND ACCOUNTING AND APPROPRIATION DATA


Contract Doc

CLIN

RCA #

RCA ACTNG #

BLI

FY

BOC

Dollars Obligated

TBD

TBD

TBD

TBD

TBD

TBD

TBD

TBD



G-3 N52.252-002 Clauses Incorporated by Reference (MAR 2001)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The full text of each clause may also be accessed electronically at this address: http://arc.westfields.net/nam.


Number

Title

N52.204-004

Contract Clause Numbering (MAR 1996)



G-4 N52.232-007 Instructions for Requesting Contract Payment (JUN 2001)
(a) All requests for invoice and contract financing payments (other than progress payments) shall be prepared on a Standard Form 1034, Public Voucher for Purchases and Services Other Than Personal, and submitted for payment to the following billing office: 
Name and address of Contracting Officer or designee:

Scott Meder, Rm 14B16E, National Reconnaissance Office, 14675 Lee Road, Chantilly VA 20151-1715

N/A
Invoices may be faxed to:  (703) 808-1623

The mode of delivery is:   mail or email (dii@nro.mil)
(b) For cost reimbursable contracts, those contractors authorized by DCAA to use Direct Billing procedures must submit only the first, final, and any award fee reconciliation payment vouchers to the billing office listed above. Unless otherwise directed by the contracting officer, submit all other vouchers, including those for or including provisional award fee, directly to the paying office specified below. Attach a copy of the DCAA Direct Billing authorization letter to the first voucher submitted to the paying office for each contract, and enter "Direct Submission Authorized" in the signature block of all vouchers submitted via Direct Billing.

 

Mode of Delivery and Address:  N/A 


The Contracting Officer Does Not require copies of vouchers submitted under Direct Billing procedures
(c) Requests for progress payments shall be prepared on a Standard Form 1443, Contractor's Request for Progress Payment, and submitted to the following billing office: 
Name and address of Contracting Officer or designee:  

Scott Meder, Rm 14B16E, National Reconnaissance Office, 14675 Lee Road, Chantilly VA 20151-1715

N/A
Invoices may be faxed to:  (703) 808-1623

The mode of delivery is:   mail or email (dii@nro.mil)
(d) The payment periods designated in the FAR Prompt Payment clause(s) contained in this contractual document will begin on the date a proper voucher or request for payment (SF 1034 or SF 1443) is received in the billing office listed above. Vouchers must be prepared in accordance with NAM Appendix N65, Contract Payments, with all charges segregated by CLIN. The following additional voucher preparation instructions and requirements for supporting documentation also apply:

 

The contractor shall bill on a monthly basis in NINE equal increments. All payment requests shall be submitted on a SF 1034 along with a monthly status report outlining all work accomplished during the period. One (1) hard copy and one (1) media copy or (1) electronic copy shall be submitted. Media copies sent by U.S. Mail should be MS Word for Windows compatible on a 1.44 MB 3.5" diskette or CD-ROM. Unclassified reports may be mailed electronically to dii@nro.mil. Classified files may be transferred through CWAN to harterw@gwan.npa.ic.gov. All media shall be virus checked with current virus detection software prior to submission. NO PAYMENTS WILL BE ALLOWED IF WORK WAS NOT PERFORMED DURING THE BILLING PERIOD.


(e) The government billing office or payment office will notify the contractor of any apparent error, defect, or impropriety in a voucher or request for payment within seven days of receipt by the billing office. Inquiries regarding vouchers or requests for payment submitted to the billing office should be directed to the government contracting officer. Inquiries regarding vouchers or requests for payment submitted directly to ROM/FIN/AP at (703) 808-4100 (unclassified) or 850-4100 (secure).


PART III - LIST OF DOCUMENTS/EXHIBITS AND OTHER ATTACHMENTS
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H-1

PART IV - REPRESENTATIONS AND INSTRUCTIONS
SECTION I - CONTRACT CLAUSES
I-1 N52.252-002 Clauses Incorporated by Reference (MAR 2001)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The full text of each clause may also be accessed electronically at this address: http://arc.westfields.net/nam.


Number

Title

52.202-1

Definitions (MAR 2001)

52.203-3

Gratuities (APR 1984)

52.203-5

Covenant Against Contingent Fees (APR 1984)

52.203-6

Restrictions on Subcontractor Sales to the Government (JUL 1995)

52.203-7

Anti-Kickback Procedures (JUL 1995)

52.203-8

Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10

Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12

Limitation on Payments to Influence Certain Federal Transactions (JUN 1997)

52.204-4

Printed or Copied Double-Sided on Recycled Paper (AUG 2000)

52.209-6

Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUL 1995)

52.215-2

Audit and Records -- Negotiation (JUN 1999)

52.215-8

Order of Precedence -- Uniform Contract Format (OCT 1997)

52.215-14

Integrity of Unit Prices (OCT 1997)

52.215-15

Pension Adjustments and Asset Reversions (DEC 1998)

52.215-18

Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions (OCT 1997)

52.222-1

Notice to the Government of Labor Disputes (FEB 1997)

52.222-26

Equal Opportunity (FEB 1999)

52.222-35

Affirmative Action for Special Disabled and Vietnam Era Veterans (APR 1998)

52.222-36

Affirmative Action for Workers with Disabilities (JUN 1998)

52.222-37

Employment Reports on Special Disabled Veterans and Veterans of the Vietnam Era (JAN 1999)

52.223-6

Drug-Free Workplace (MAY 2001)

52.223-14

Toxic Chemical Release Reporting (MAY 2001)

52.225-13

Restrictions on Certain Foreign Purchases (JUL 2000)

52.227-1

Authorization and Consent (JUL 1995)

52.227-2

Notice and Assistance Regarding Patent and Copyright Infringement (AUG 1996)

52.227-10

Filing of Patent Applications -- Classified Subject Matter (APR 1984)

52.227-12

Patent Rights -- Retention by the Contractor (Long Form) (JAN 1997)

52.227-14

Rights in Data -- General (JUN 1987)

52.229-5

Taxes -- Contracts Performed in U.S. Possessions or Puerto Rico (APR 1984)

52.230-2

Cost Accounting Standards (APR 1998)

52.230-3

Disclosure and Consistency of Cost Accounting Practices (APR 1998)

52.230-6

Administration of Cost Accounting Standards (NOV 1999)

52.232-2

Payments under Fixed-Price Research and Development Contracts (APR 1984)

52.232-24

Prohibition of Assignment of Claims (JAN 1986)

52.232-25

Prompt Payment (MAY 2001)

52.233-3

Protest after Award (AUG 1996)

52.242-13

Bankruptcy (JUL 1995)

52.245-2

Government Property (Fixed-Price Contracts) (DEC 1989)

52.245-17

Special Tooling (DEC 1989)

52.246-23

Limitation of Liability (FEB 1997)

52.249-1

Termination for Convenience of the Government (Fixed-Price) (Short Form). (APR 1984)

52.249-2

Termination for Convenience of the Government (Fixed-Price) (SEP 1996)

52.249-9

Default (Fixed-Price Research and Development) (APR 1984)

52.253-1

Computer Generated Forms (JAN 1991)

N52.203-001

NRO Hotline (OCT 1997)

N52.203-003

Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies (DEC 1999)(DFARS 252.203-7001)

N52.203-004

Personal Conduct (APR 1997)

N52.204-001

Security Requirements (MAR 2000)

N52.204-003

Special Notification And Approval Requirements (JUN 2001)

N52.209-001

Acquisition From Subcontractors Subject To On-Site Inspection Under The Intermediate-Range Nuclear Forces (INF) Treaty (MAR 1996)

N52.209-008

Organizational Conflicts Of Interest: General (MAR 1996)

N52.215-002

Intention To Use Consultants (JAN 1998)

N52.215-018

Cost Estimating System Requirements (JAN 1998) (DFARS 252.215-7002)

N52.223-006

Contractor Compliance with Enviromental Safty and Health, and System Safty Requirements (OCT 1997)

N52.227-001

Non-Estoppel (MAR 1996) (DFARS 252.227-7000)

N52.227-036

Data Requirements (MAR 1996)

N52.232-012

Consideration And Payment - Services (MAR 1996)

N52.233-002

Disputes (MAY 1996)

N52.233-004

Request for Dispute Resolution (SEP 2000)

N52.242-001

Authority And Designation Of A Contracting Officer's Technical Representative (COTR) (MAR 1996)

N52.242-002

Contractor Performance Assessment Review (SEP 2000)

N52.244-001

Subcontracts (Educational Institutions) (SEP 1996)

N52.245-005

Prohibition on Contractor Acquisition of Personal Property for Use by Government Employees (JUN 2001)

N52.245-006

Identification of Promotional Items (DEC 2000)

N52.245-007

Contractor Requests for Government-Owned Equipment (JUN 2001)




















I-2 52.249-8 Default (Fixed-Price Supply and Service) (APR 1984)
(a) (1) The Government may, subject to paragraphs (c) and (d) of this clause, by written notice of default to the Contractor, terminate this contract in whole or in part if the Contractor fails to-- 

  1. Deliver the supplies or to perform the services within the time specified in this contract or any extension; 

  2. Make progress, so as to endanger performance of this contract (but see subparagraph (a)(2) of this clause); or 

  3. Perform any of the other provisions of this contract (but see subparagraph (a)(2) of this clause). 

(2) The Government's right to terminate this contract under subdivisions (a)(1)(ii) and (1)(iii) of this clause, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of the notice from the Contracting Officer specifying the failure. 


(b) If the Government terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, supplies or services similar to those terminated, and the Contractor will be liable to the Government for any excess costs for those supplies or services. However, the Contractor shall continue the work not terminated. 
(c) Except for defaults of subcontractors at any tier, the Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include (1) acts of God or of the public enemy, (2) acts of the Government in either its sovereign or contractual capacity, (3) fires, (4) floods, (5) epidemics, (6) quarantine restrictions, (7) strikes, (8) freight embargoes, and (9) unusually severe weather. In each instance the failure to perform must be beyond the control and without the fault or negligence of the Contractor. 
(d) If the failure to perform is caused by the default of a subcontractor at any tier, and if the cause of the default is beyond the control of both the Contractor and subcontractor, and without the fault or negligence of either, the Contractor shall not be liable for any excess costs for failure to perform, unless the subcontracted supplies or services were obtainable from other sources in sufficient time for the Contractor to meet the required delivery schedule. 
(e) If this contract is terminated for default, the Government may require the Contractor to transfer title and deliver to the Government, as directed by the Contracting Officer, any (1) completed supplies, and (2) partially completed supplies and materials, parts, tools, dies, jigs, fixtures, plans, drawings, information, and contract rights (collectively referred to as "manufacturing materials" in this clause) that the Contractor has specifically produced or acquired for the terminated portion of this contract. Upon direction of the Contracting Officer, the Contractor shall also protect and preserve property in its possession in which the Government has an interest. 
(f) The Government shall pay contract price for completed supplies delivered and accepted. The Contractor and Contracting Officer shall agree on the amount of payment for manufacturing materials delivered and accepted and for the protection and preservation of the property. Failure to agree will be a dispute under the Disputes clause. The Government may withhold from these amounts any sum the Contracting Officer determines to be necessary to protect the Government against loss because of outstanding liens or claims of former lien holders. 
(g) If, after termination, it is determined that the Contractor was not in default, or that the default was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for the convenience of the Government. 
(h) The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract. 
I-3 N52.209-013 Enabling Clause for Prime and Support Contractor Relationships (JUN 2001)
(a) The Government has or may enter into contracts with one or more of the following companies to provide Contracted Advisory and Assistance Services (CAAS) and/or Systems Engineering and Technical Assistance (SETA):

Advent Systems, Inc

Titan Systems Corporation, Solutions Engineering Division

(b) In the performance of this contract, the contractor agrees to cooperate with the companies listed above (hereafter referred to as CAAS/SETAs). Cooperation includes allowing observation of technical activities by appropriate CAAS/SETA technical personnel; discussing technical matters related to this program; responding to invitations from authorized CAAS/SETA personnel to attend meetings; and providing access to technical information and research and development planning data. The contractor shall provide CAAS/SETA personnel access to data such as, but not limited to, design and development analyses; test data and results; equipment and process specifications; test and test equipment specifications; procedures, parts, and quality control procedures; records and data; manufacturing and assembly procedures; and schedule and milestone data. CAAS/SETA personnel engaged in general systems engineering and integration effort are normally authorized access to any technical information pertaining to this contract. However, exceptions, such as the case where the contractor seeks to preclude CAAS/SETA personnel from having access to contractor trade secrets, will be handled on a case-by-case basis. If the contractor seeks to limit distribution of data to Government personnel only, the contractor must submit this request in writing to the contracting officer.


(c) The contractor further agrees to include in each subcontract a clause requiring compliance by the subcontractor and succeeding levels of subcontractors with the response and access provisions of paragraph (b) above, subject to coordination with the contractor. This agreement does not relieve the contractor of responsibility to manage the subcontracts effectively and efficiently, nor is it intended to establish privity of contract between the Government or CAAS/SETAs and such subcontractors.
(d) CAAS/SETA personnel are not authorized to direct the contractor in any manner. The contractor agrees to accept technical direction as follows:
(1) Technical direction under this contract will be given in accordance with the contract clause entitled Authority and Designation of the Contracting Officer's Technical Representative.
(2) Whenever it becomes necessary to modify the contract and redirect the effort, a change order signed by the contracting officer or supplemental agreement signed by both the contracting officer and the contractor will be issued.
(e) CAAS/SETA contracts will contain an organizational conflict of interest clause that requires the CAAS/SETA contractor to protect contract data and prohibits the CAAS/SETA contractors from using such data for any purpose other than that for which the data was presented.

I-4 N52.211-004 Usage Of The Metric System Of Measurement (SI) (MAR 1996)
(a)  Basic requirement.  This contract requires, unless authorized in paragraph (d) below, that all supplies, components, reports, documentation, or services which are designed, fabricated, assembled, delivered or performed under this contract shall utilize the "International System of Units" (SI). 
(b) The "International System of Units" is as established by the General Conference of Weights and Measures in 1960; it is also known as "System International (SI)" or "Metric System"; and it is interpreted for US usage by the Department of Commerce's Interpretation of the International System of Units for the United States as printed in Federal Register Volume 55, Page 52242, Dec. 20, 1990, and supplemented for the Federal Government's usage by the General Services Administration's Federal Standard 376, Preferred Metric Units of General Use by the Federal Government
(c)  Conflict of interest.  In the event there is a conflict between the International System of Units; 55 FR 52242, Dec. 20, 1990; Federal Standard 376; or the contract schedule, the order of precedence in resolving the conflict shall be contract schedule first, followed by Federal Standard 376; 55 FR 52242, Dec. 20, 1990; and International System of Units in descending importance. 
(d)  Exemption to requirement.  The following supplies, components, reports, documentation, or services that are designed, fabricated, assembled, delivered or performed under this contract are exempt from the requirements of this clause: 
The contractor should submit a request for exemption to the Contracting Officer whenever compliance is either not possible, impracticable, or otherwise not in the Government's best interest. The scope of the request shall be limited to only those items negatively impacted by the requirement.

I-5 N52.211-007 NRO Standards Document Compliance (SEP 2000)
(a) This contract requires, unless authorized in paragraph (b) below, that all supplies, components, reports, documentation, data, or services which are designed, fabricated, assembled, delivered, or performed under this contract shall comply with the NRO Standards Document, Version  1.0 dated 24 Mar 2000. The NRO Standards Document can be accessed directly through the NRO Contractor Wide-Area Network (CWAN) Homepage of the Corporate System Engineer at http://nro_ddse.tasc.npa.gov/default.htm, or obtained in CD-ROM format or paper copy by contacting the Office of Corporate System Engineering at 850-6920 (secure) or (703) 808-6920 (non-secure).  
(b) The following supplies, components, reports, documentation, data, or services that are designed, fabricated, assembled, delivered or performed under this contract are exempt from the requirements of this clause:
(c) The contractor should submit a request for exemption to the contracting officer whenever compliance with the NRO Standards Document is impossible, impracticable, or otherwise not in the best interests of the Government. The scope of the request shall be limited to only those items negatively impacted by the requirement.

I-6 N52.215-006 Incorporation Of Section K, Representations, Certifications, And Other Statements Of Offerors (DEC 1998)
Section K, dated TBD, completed and submitted with the contractor's proposal, in support of this effort, or on file with the contracting officer's Directorate/Office, is incorporated herein by reference and made a part of this contract. 

I-7 N52.223-005 Prohibition On Storage And Disposal Of Toxic And Hazardous Materials (OCT 1997)
(a) Definitions. As used in this clause: 
(1) "Storage" means a non-transitory, semi-permanent or permanent holding, placement, or leaving of material. It does not include a temporary accumulation of a limited quantity of a material used in or a waste generated or resulting from authorized activities, such as servicing, maintenance, or repair of Government items, equipment, or facilities.

 

(2) "Toxic or hazardous materials" means those materials identified in the "EPA Title III List of Lists". 


(b) The contractor is prohibited from transporting, storing, disposing or using toxic or hazardous materials in performing this contract except for those materials listed in (c) below or when authorized in writing by the Contracting Officer. 
(c) Toxic and hazardous materials authorized for use in the performance of this contract are as listed below: 

I-8 N52.232-005 Limitation Of Government's Obligation (MAR 1996) (DFARS 252.232-7007)
(a) The following contract line item(s) are incrementally funded. For these item(s), the sum(s) applicable to the total price of each line item is presently available for payment and allotted to this contract as indicated below. An allotment schedule is set forth in paragraph (i) of this clause.
(b) For item(s) identified in paragraph (a) of this clause, the contractor agrees to perform up to the point at which the total amount payable by the Government, including reimbursement in the event of termination of those item(s) for the Government's convenience, approximates the total amount currently allotted to the contract. The contractor will not be obligated to continue work on those item(s) beyond that point. The Government will not be obligated in any event to reimburse the contractor in excess of the amount allotted to the contract for those item(s) regardless of anything to the contrary in the clause entitled 'Termination for Convenience of the Government." As used in this clause, the total amount payable by the Government in the event of termination of applicable contract line item(s) for convenience includes costs, profit, and estimated termination settlement costs for those item(s). 
(c) Notwithstanding the dates specified in the allotment schedule in paragraph (i) of this clause, the contractor will notify the Contracting Officer in writing at least ninety days prior to the date when, in the contractor's best judgment, the work will reach the point at which the total amount payable by the Government, including any cost for termination for convenience, will approximate 85 percent of the total amount then allotted to the contract for performance of the applicable item(s). The notification will state (1) the estimated date when that point will be reached and (2) an estimate of additional funding, if any, needed to continue performance of applicable line items up to the next scheduled date for allotment of funds identified in paragraph (i) of this clause, or to a mutually agreed upon substitute date. The notification will also advise the Contracting Officer of the estimated amount of additional funds that will be required for the timely performance of the item(s) funded pursuant to this clause, for a subsequent period as may be specified in the allotment schedule in paragraph (i) of this clause, or otherwise agreed to by the parties. If after such notification additional funds are not allotted by the date identified in the contractor's notification, or by an agreed substitute date, the Contracting Officer will terminate any item(s) for which additional funds have not been allotted, pursuant to the clause of this contract entitled "Termination for Convenience of the Government." 
(d) When additional funds are allotted for continued performance of the contract line item(s) identified in paragraph (a) of this clause, the parties will agree as to the period of contract performance which will be covered by the funds. The provisions of paragraph (b) through (d) of this clause will apply in like manner to the additional allotted funds and agreed substitute date, and the contract will be modified accordingly. 
(e) If, solely by reason of failure of the Government to allot additional funds, by the dates indicated below, in amounts sufficient for timely performance of the contract line item(s) identified in paragraph (a) of this clause, the contractor incurs additional costs or is delayed in the performance of the work under this contract and if additional funds are allotted, an equitable adjustment will be made in the price or prices (including appropriate target, billing, and ceiling prices where applicable) of the item(s), or in the time of delivery, or both. Failure to agree to any such equitable adjustment hereunder will be a dispute concerning a question of fact within the meaning of the clause entitled "Disputes." 
(f) The Government may at any time prior to termination allot additional funds for the performance of the contract line item(s) identified in paragraph (a) of this clause. 
(g) The termination provisions of this clause do not limit the rights of the Government under the clause entitled "Default." The provisions of this clause are limited to the work and allotment of funds for the contract line item(s) set forth in paragraph (a) of this clause. This clause no longer applies once the contract is fully funded except with regard to the rights or obligations of the parties concerning equitable adjustments negotiated under paragraphs (d) or (e) of this clause. 
(h) Nothing in this clause affects the right of the Government to terminate this contract pursuant to the clause of this contract entitled 'Termination for Convenience of the Government." 
(i) The parties contemplate that the Government will allot funds to this contract in accordance with the following schedule: 


CLIN

AMOUNT

OBLIGATION

TBD TBD TBD

 

I-9 N52.245-001 Property Administration And Control (JUN 2001)


(a) For the purposes of this contract, property administration authority is delegated to the following NRO Property Analyst:

TBD

(b) The contractor shall maintain adequate property control procedures, records, and a system of identification for all Government property accountable to this contract in accordance with FAR Part 45 and NAM Part N45.


(c) The contractor shall provide the name, address, and telephone number of the company official responsible for establishing and maintaining control of Government property under this contract to the NRO Property Analyst listed above within thirty (30) days after receipt of this contract.


SECTION J - LIST OF ATTACHMENTS
J-1 Incorporation Of Attachments And Exhibits
The Attachments and/or Exhibits listed below are incorporated herein and made part hereof: 


Attachment Number

Description

No. Pages




NOT APPLICABLE TO THIS CONTRACT







Page of 15

ATTACHMENT 2 BAA 000-02-R-0008


База данных защищена авторским правом ©shkola.of.by 2016
звярнуцца да адміністрацыі

    Галоўная старонка